Which of the following contracts has the MOST risk for the Buyer
A. Cost plus fixed fee (CPFF)
B. Time and Materials (T&M)
C. Cost plus award fee (CPAF)
D. Fixed price (FP)
As per head first it is T&M. But I choose CPFF. Rita and PMBOK also says the same
Can anyone explain this?
Forums:


admin
Tue, 07/23/2013 - 07:33
Permalink
Please search before you
Please search before you post. Many posts already related to this, you can read and benefit.