1. A R&D project manager wants to go for the contracting, he picks
the preferred seller who is working with his organization for long
time. He want to have a good relation with seller and get his work done
as he need. What type of contract he will sign-up with the seller.
a. Fixed price plus incentive contracts
b. Cost plus fixed fee (CPFF)
c. Cost plus incentive fee (CPIF)
d. Cost plus Award Fee (CPAF)
a. Fixed price plus incentive contracts
b. Cost plus fixed fee (CPFF)
c. Cost plus incentive fee (CPIF)
d. Cost plus Award Fee (CPAF)


Since its research project
In R&D projects the scope