What is not the purpose of Configuration control when Configuration management is applied in a project?
A) Verification that the configuration identification for a configuration item is accurate, complete, and will meet specified program needs.
B) Ensuring that proposed and approved changes to configuration items are fully analyzed.
C) Ensuring that proposed and approved changes to configuration items are fully documented.
D) Managing and controlling the frequently requested changes to a project by applying agreed rules.
Ans) A
Please help me to arrive at this answer.


admin
Thu, 06/24/2010 - 05:33
Permalink
First of all I dont think
First of all I dont think this can be a question in real exam, since one is not expected to know about configuration control as such. But since you have asked. Config control does deal with Analyzing and documenting propose and approved changes and managing the changes whic his point B , C and D
To know more about this and diff between configuration control and managment, please refer to this page
http://www.hyperthot.com/pm_cm.htm
swet
Thu, 06/24/2010 - 15:13
Permalink
The others B, C and D are
The others B, C and D are more appropriate to the Configuration Managment....so the answer is A.