Closure question..D or A with expln

Question: A project manager is in the final closure phase of the project . Which of
the following should he do FIRST as part of the project closure activity?


Options:
A. Get formal sign off from the customer to confirm customer acceptance of final
deliverable
B. Measure customer satisfaction as a key performance indicator of project's success
C. Hand off completed project deliverables to operations and management
D. Measure project scope against project management plan

He should do FIRST as part of the project closure activity:

D Measure project scope against project management plan

p 99 , 4.6 3rd sentence

 

-----

then A, 

then C

then B

refer

http://er-sspawar.blogspot.in/2013/02/closing-most-debated-and-low-scori...

option D)

D should be the right answer.

 

Pawar, isnt A part of Verify Scope? 

 D then A , both activities are parts of close project/phase

2nd activity of p100 -getting final sign off documents

and fig 4.13

5.4.3.1/p125

 D, then A. 

sspawar's explanation is very clear. Please read his blog, it is very informative. 

Isn't D part of Verify Scope process?

 Im still confused with the Project Closing process. Is there any sequence of Process that need to follow or just need to meet the required steps .


In PMBOK its not mentioned in any sequential steps and RITA : Some thing more been added. Can some one put The complete must do steps with sequence if any here please


Question from Simple Learn Free mock exam .


Which one of the following is the last step of project closing?


A .Archive Project Documents
B .Measure customer satisfaction at the end of the project
C .Client appreciates your product
D .Lessons learnt are documented
 
Explanation:


The right answer is B. All of the stated options are activities conducted during project closing. Measure customer satisfaction at the end of the project is the last step in the closing process group. This is as per the new changes suggested by the PMI RDS Study.
 

 Im still confused with the Project Closing process. Is there any sequence of Process that need to follow or just need to meet the required steps .


In PMBOK its not mentioned in any sequential steps and RITA : Some thing more been added. Can some one put The complete must do steps with sequence if any here please


Question from Simple Learn Free mock exam .


Which one of the following is the last step of project closing?


A .Archive Project Documents
B .Measure customer satisfaction at the end of the project
C .Client appreciates your product
D .Lessons learnt are documented
 
Explanation:


The right answer is B. All of the stated options are activities conducted during project closing. Measure customer satisfaction at the end of the project is the last step in the closing process group. This is as per the new changes suggested by the PMI RDS Study.
 

Thank you Pawarji