Question: A project manager is in the final closure phase of the project . Which of
the following should he do FIRST as part of the project closure activity?
Options:
A. Get formal sign off from the customer to confirm customer acceptance of final
deliverable
B. Measure customer satisfaction as a key performance indicator of project's success
C. Hand off completed project deliverables to operations and management
D. Measure project scope against project management plan
Forums:


sspawar
Mon, 02/25/2013 - 14:11
Permalink
He should do FIRST as part of
He should do FIRST as part of the project closure activity:
D Measure project scope against project management plan
p 99 , 4.6 3rd sentence
-----
then A,
then C
then B
refer
http://er-sspawar.blogspot.in/2013/02/closing-most-debated-and-low-scori...
sunitaPMP
Mon, 02/25/2013 - 17:42
Permalink
option D)
option D)
raza82
Mon, 02/25/2013 - 18:53
Permalink
D
D should be the right answer.
Pawar, isnt A part of Verify Scope?
sspawar
Mon, 02/25/2013 - 23:57
Permalink
D then A , both activities
D then A , both activities are parts of close project/phase
2nd activity of p100 -getting final sign off documents
and fig 4.13
5.4.3.1/p125
mercurie
Tue, 02/26/2013 - 06:03
Permalink
D, then A. sspawar's
D, then A.
sspawar's explanation is very clear. Please read his blog, it is very informative.
ritu81
Thu, 02/28/2013 - 09:37
Permalink
Isn't D part of Verify Scope
Isn't D part of Verify Scope process?
Sree
Thu, 02/28/2013 - 10:51
Permalink
Still Confused with the Project Closing Steps
Im still confused with the Project Closing process. Is there any sequence of Process that need to follow or just need to meet the required steps .
In PMBOK its not mentioned in any sequential steps and RITA : Some thing more been added. Can some one put The complete must do steps with sequence if any here please
Question from Simple Learn Free mock exam .
Which one of the following is the last step of project closing?
A .Archive Project Documents
B .Measure customer satisfaction at the end of the project
C .Client appreciates your product
D .Lessons learnt are documented
Explanation:
The right answer is B. All of the stated options are activities conducted during project closing. Measure customer satisfaction at the end of the project is the last step in the closing process group. This is as per the new changes suggested by the PMI RDS Study.
Sree
Thu, 02/28/2013 - 10:51
Permalink
Still Confused with the Project Closing Steps
Im still confused with the Project Closing process. Is there any sequence of Process that need to follow or just need to meet the required steps .
In PMBOK its not mentioned in any sequential steps and RITA : Some thing more been added. Can some one put The complete must do steps with sequence if any here please
Question from Simple Learn Free mock exam .
Which one of the following is the last step of project closing?
A .Archive Project Documents
B .Measure customer satisfaction at the end of the project
C .Client appreciates your product
D .Lessons learnt are documented
Explanation:
The right answer is B. All of the stated options are activities conducted during project closing. Measure customer satisfaction at the end of the project is the last step in the closing process group. This is as per the new changes suggested by the PMI RDS Study.
sspawar
Thu, 02/28/2013 - 11:12
Permalink
READ THIS BLOG
READ THIS BLOG POST
http://er-sspawar.blogspot.in/2013/02/closing-most-debated-and-low-scori...
Sree
Thu, 02/28/2013 - 12:05
Permalink
Thank you Ji .
Thank you Pawarji