Closing Question - Help

Hi Guys, need help with this question:

One way the Close Project or Phase process differs from Close Procurement is:

A)Procurement closure involves verification that all work and deliverables are acceptable, where Close Project
or Phase does not

B)Close Project or Phase is only a subset of Close Procurement

C)Procurement closure means verifying that the project is complete or terminated; Close Project or
Phase is the process of tying up all of the activities for every management process group

D)Procurement closure is performed by the seller, Close Project or Phase is performed by the buyer

Which one is the right answer? and some explanation would help.

Thank you for your time.

admin's picture

Not sure about this

C looks more relevant.

A is incorrect statement close project or phase verify that all work and deliverable are acceptable.
B. is incorrect close procurement is subset of close project or phase
C. looks correct since both statements about close project and close procurement are true.
D. close project or phase is performed by seller. and close procurement is performed by buyer. (in PMBOK only in procurement chapter we act like buyer est all chapters are for sellers.)

please tell me what is the right answer.