Can someone order the the below closing activities in the right sequence(first to last)

 ·         Confirm all the requirement have met

·        

Close procurement  


o  

Verify product


o  

Issue formal acceptance


o  

Conduct procurement audit


o  

Report final contract performance


o  

Document lesson learned


o  

Perform financial closure of contract

·        

Get formal acceptance of the product

·        

Measure customer satisfaction

·        

Perform financial closure of project

·        

Report final project performance

·        

Documents lesson learned

·        

Update project records

·        

Archive project records

·        

Hand off the completed product

Release the team