Close Procurements

Question: Since the buyer could not meet the requirements of the contract, you (the seller) want to terminate the contract early. This is done in the:

Choice 1. Plan Procurement Management process

Choice 2. Control Procurements process

Choice 3. Close Procurements process

Choice 4. Conduct Procurements process

What will be the answer?