Close Procurements

Question: Since the buyer could not meet the requirements of the contract, you (the seller) want to terminate the contract early. This is done in the:

Choice 1. Plan Procurement Management process

Choice 2. Control Procurements process

Choice 3. Close Procurements process

Choice 4. Conduct Procurements process

What will be the answer?

It would be nice to see more Control Procurements process. - James D. Sterling