A change in your project schedule has resulted in increased cost and risk. It has also impacted your resource plan. To coordinate changes across the entire project, you will need to rely on which of the following: |
|
|
|
Change control system |
|
|
|
Perform Integrated Change Control |
|
|
|
Change requests |
|
|
|
Changes to project plan baselines |


sathya737
Wed, 05/08/2013 - 12:27
Permalink
I think we should do Perform Integrated Change Control
hi
rwmv
Wed, 05/08/2013 - 12:41
Permalink
Perform Integrated Change
Perform Integrated Change Control as its impacted various process groups.
crushPMP
Wed, 05/08/2013 - 12:57
Permalink
B?
B?
BK
Wed, 05/08/2013 - 13:21
Permalink
yes..B is the correct
yes..B is the correct ans..Can somebody explain why not A?
don't we need change control system for coordinating changes?
Geethika
Wed, 05/08/2013 - 13:41
Permalink
yes..
Yes. we may need change control system tool for coordinating changes.
But the Q asks for what we need to rely on? It will be "Perform Integrated Change control" process