Which of the following is not true about change requests?

A.      Change Request can be verbally communicated.

B.      Change Control System may have a provision for automatic approval of defined category of changes.

C.      All change request result  in updates to project baselines.

D.      Request for change can be direct or indirect, externally or internally initiated.

 

 

3.5
Your rating: None Average: 3.5 (2 votes)

A and B are confusing.

A and B are confusing. However, I would go with B as there should be impact done for the changes so automatic approval of the request should not be done.

 

My choice will be C

 only because of the word "ALL".  

bunnynbear's picture

C is correct

PMBOK Page 92 4.5.3 says:

If a change request is deemed feasible but outside the project scope, its approval requires a baseline
change.

So if a change request is not outside the project scope, it won't involve a baseline change.

C is correct

I too think C is correct !!! All CRs may not need a baseline change.

C is correct

I too think C is correct !!! All CRs may not need a baseline change.

C

 D doesnot make any sense...

 

A and B are true...

C is the right answer, many

C is the right answer, many of you got it right :)

C it is

Yes, C is the correct option. And D does make sense. Its correct as well in reference to Integrated Change control, hence incorrect. KK....

My Choice is A

As all the Change Requests have to be documented, even though they are emergency Change Requests.

The answer is....

Hi pri_july,

 

The question talks on the commnication of change request. it can be done verbally and then the process of documentation starts.

 

Hence, the correct answer is C!

 

Hope you agree Sir/Madam?

 

KK

Thanks..got it!!

Thanks..got it!!

The Correct Answer is C

The correct answer is C, now the true REASON why C is that - "Change Request" in its state could either be approved or rejected by the ICCB, and only "APPROVED CHANGE REQUESTS" have subsequent change impacts on the baselines. Hence, C is the "NOT TRUE" statement. Remember, the question asks for the "not true" option.

 

My advise is just buy 2 test

My advise is just buy 2 test from PM Study and maybe 1 from some other source. Kurti

Thesis writing services

Thesis writing services

Fantastic goods from you, man. Ive study your stuff ahead of and you're just as well amazing. I enjoy what you've got right here, adore what you're stating and the way you say it. You make it entertaining and you even now manage to help keep it wise.

C is the best answer

Choice A is true. Change request can be verbally communicated (what is wrong in verbally communicating? communicating esentially differs from formally submitting, in most cases, change requests are verbally communicated before they are formally written in paper.)

Choice B is WRONG however it does not speak about change request but rather change control system. The question clearly asks about "change request"

Choice C- is wrong, only the "approved change requests"have resulting chnage in the project baselines. Since this speaks about change request, then it must be the best choice.

Choice D is true.  

sspawar's picture

1040 - C is right answer

So far 1040 have been viewed.

great participation.

Around 15 have replied, most of answer is C.

All change request could not be result in project baselines.

Option B - is around the subject line. because questioner is specifying in subject matter that  " about change request which one is not true". Hence option B is acceptable as a true statement .  Also he is talking - some defined change requests may be approved -----

----, in other words. it means it is related to change requests.

 

Regards