
Can't see why Option B is correct. pls help
Submitted by tonsi on Wed, 11/28/2007 - 21:44.
The following three tasks form the entire critical path of the project network. The three estimates of each of these tasks are tabulated below. How long would the project take to complete expressed with an accuracy of one standard deviation?
Task Optimistic Most likely Pessimistic
A
15
25
47
B
12
22
35
C
16
27
32
A. 75.5
B. 75.5 +/- 5.08
C. 75.5 +/- 8.5
D. 75.5 +/- 2.83


auto cleansed :)
auto cleansed
(there is no button for delete)
Can't see why Option B is correct. pls help
probability
Probability calculation
75.5 looks right based upon the calculation for PERT:
(P + O + (4*M))/6
(114 + 43 + (4 * 74))/6 = 75.5
But....
Regarding the post above with the standard deviation calculation:
I'm a bit confused by this - isn't the "standard deviation" calculation for this type of question/problem: (P-O)/6 ???
I have this listed in different study literature (one which I downloaded from this site).
Granted, it doesn't fit this answer, but where does it fit in?
Should I be prepared to use the more traditional standard deviation formula?
..just wondering....Thanks!