Budget Estimate as per PMBOK
Submitted by manishpmp on Mon, 07/09/2012 - 14:35
Can someone pleas help me with the Budget Estimate as per PMBOK. Are the following correct.
ROM = +/- 50%
Budget Estmate = -10% to 25%
Definitive Estimate = -5% to 10%
Kindly let me know if these are correct to use in PMP exam.


sspawar
Mon, 07/09/2012 - 16:33
Permalink
PMBOK says
What PMBOK SAYS is here:
The accuracy of a project estimate will increase as the project progresses through the project life cycle. Hence cost estimating is an iterative process from phase to phase.
For example, a project in the initiation phase could have a rough order of magnitude (ROM) estimate in the range of +/-50%.
Later in the project, as more information is known, estimates could narrow to a range of +/-10%.
In some organizations, there are guidelines for when such refinernents can be rnade and the degree of accuracy that is expected.
Other statements are irrelevant to PMP EXAM.
Regards
SSP