Appropriate EAC Formula
Submitted by Vishwanath on Sun, 07/07/2013 - 14:25
After the last Project last project meeting your sponsor has asked you to give her anew estimate of the cost at the end of the project. This is because during the meetingit was found that so much has gone wrong until now, that the numbers are probablyoff. It is expected, that from now on things will progress normally. You gather allthe necessary numbers from your PMIS. Which formula will you use to create theexpected total cost of the project?
A.) EAC = BAC/CPI
B.) EAC = AC+ETC
C.) EAC = AC+BAC-EV
D.) ETC = EAC-AC
Key word to attempt this question?
Forums:


pmpnewster
Sun, 07/07/2013 - 17:28
Permalink
B Regards.
B
Regards.
pmpnewster
Mon, 07/08/2013 - 01:59
Permalink
I can now see why choice C
I can now see why choice C makes sense.
Reason: We use a new bottoms-up estimate when the original estimate was flawed. In the present case, the question does not any anything like that.
All we know is that things have gone wrong till now but that they would proceed normally henceforth. So we should use EAC = AC + (BAC-EV).
Moral of the story: Unless the question explicitly points to the original estimate being flawed (or lost, or never performed) we should not go for a new bottoms-up ETC estimate.
Regards.
Vishwanath
Sun, 07/07/2013 - 18:17
Permalink
C is the correct answer
C is the correct answer
tweinborg
Sun, 07/07/2013 - 18:54
Permalink
Answer B
I interpret this as initial estimates being flawed so I would think B would be the correct formula.
Tina W.
th9063
Sun, 07/07/2013 - 21:48
Permalink
B......new estimateth
B......new estimate
th
pmpnewster
Mon, 07/08/2013 - 01:58
Permalink
I can now see why choice C
I can now see why choice C makes sense.
Reason: We use a new bottoms-up estimate when the original estimate was flawed. In the present case, the question does not any anything like that.
All we know is that things have gone wrong till now but that they would proceed normally henceforth. So we should use EAC = AC + (BAC-EV).
Moral of the story: Unless the question explicitly points to the original estimate being flawed (or lost, or never performed) we should not go for a new bottoms-up ETC estimate.
Regards.