Hi,
I was filling in the PMP application form online. had a doubt regarding this,
what should be the division of hours for each of the 5 PRocess groups
Initiation, Planning, Control, Execution, Closure
Thanks a lot
Forums:


admin
Thu, 07/02/2009 - 08:36
Permalink
There are no rules as far as
There are no rules as far as distributing hours in these 5 areas. You have to put what you have actually spent on these areas. You can put zero in one area , if that is actual.