AND C OR D?

The client demands changes to the product specification that will add only two weeks to the critical path. Which of the following is the best thing for the project manager to do?

 

A. Compress the schedule 2 weeks.

B. Cut scope to gain 2 weeks.
C. Consult with project sponsor about options.
D. Advise the client of the impact of the change 

Ans:

D

The impact of the changes should be communicated beforehand before the Change request is created and sent to CCB.