The activity "Ship Container" in your network diagram has an early start of day 17

The activity "Ship Container" in your network diagram has an early start of day 17, a late start of day 22 and a late finish of day 37. What is the activity duration?
 
a. 15 days
b. 16. days
c. 59 days
d. 14 days
 
The correct answer is given as "16 days" based on formula LF - LS + 1
I though the correct answer is 15 days based on formula LF - LS
 
How did he decided to add 1 to it? I know I have seen this formula also where you start forward pass of network diagram using "1" instead of "0" but how can you say by looking at this question that you should add 1?

http://u.rmcproject.com/tips/pdfs/Two%20Methods%20to%20Calculate%20Pass.pdf

Try the link above, it explained this issue pretty well for me.

 

 But in this question, how to identify which method to use.

For this you will have to go in back ground from where it came, what method (formula) he is adapting?

always follow 0 start method in exam -according to that answer is 15 days.

its a common debating subject but earlier i have posted the PMI  view.

search it from search box - put keay word - PMI SAYS START WITH 0.

REGARDS