Activity duration
Submitted by celebi01 on Thu, 05/02/2013 - 19:57
Hello, I have a question about activity duration. I'm studying in Rita's book. Here the activity duration is assumed EF-ES or LF-EF. In some Internet exercises I find a different calculation: EF-LF+1. Which is the right one? Why there is this difference? Thanks
Forums:


Hemant Tandon
Fri, 05/03/2013 - 00:04
Permalink
My guess is, you are getting
My guess is, you are getting confused between formula for calculating float and fomula for calculating activity duration. I am saying so because, LF-EF (mentioned in your question) is a formula to calculate Float of an activity and not the duration of it.
Fomula for calculating activity duration is EF-ES+1 or LF-LS+1.
For example:-
So, effectively your team will be working for 4 days (2nd, 3rd, 4th and 5th) and not 3 days.
Regards,
Hemant, PMP
celebi01
Fri, 05/03/2013 - 06:24
Permalink
Thank you for
Thank you for explanation.Your approach is different from Rita's chart: this is the reason of my confusion. I think that the difference is because Rita start from 0, not from 1, in the critical path calculation. ex activita A (with duration 4) start at 0 and end at 4. So the duration is EF-ES=4-0.
Other exercises in other books use the formula EF-ES+1. My doubt is: wich is the correct approach for PMP exam?
Thanks
sspawar
Fri, 05/03/2013 - 06:37
Permalink
refer blog dated
refer blog dated 26th of Dec 12
on
er-sspawar.blogspot.in