activity to be shortened
based on the details below, if you needed to shorten the duration of the project, which activity would you try to shorten?
Activity Preceding Activity Duration
Start None 0
A Start 1
B Start 2
C Start 6
D A 10
E B, C 1
F C 2
G D 3
H E 9
I F 1
End G,H,I 0
A)Activity B
B)Activity C
C)Activity H
D)Activity D


sanskrit
Mon, 06/03/2013 - 03:30
Permalink
B
Actvity C
vijayavadrevu
Mon, 06/03/2013 - 06:12
Permalink
From the diagram, there are 4
From the diagram, there are 4 paths,
Start -> C -> F -> I -> End = 6+2+1 = 9days
Start -> C -> E -> H -> End = 6+1+9 = 16days
Start ->B-> E -> H -> End = 2+1+9 = 12days
Start -> A -> D -> G -> End = 1+10+3 = 14days
Since C, E, H are on critical path, we can shorten the duration of C or H. When duration oh H is 9 days and duration of C is 6 days, why can't we select activity H
Can you please explain?
I forgot to mention your choice of activity C is correct
cnppmp
Mon, 06/03/2013 - 11:16
Permalink
Is it H?
H because it doesn't have impact on any other path. C would have impact on path BEH as it comes closer to crtical path CEH.
And ADG also near to to crtical path CEH. Then it would be more diffcult to manage the activities with so closer to critical path. I would think it has more risk.
Regards
CN Patil