You and a team member are having a disagreement

You and a team member are having a disagreement about some terminology with project management documentation. He asks you where the project management plan is, and when you provide it to him, he says, ‘’I don’t need a thesis. “ You don’t understand why he is saying this. Which answer below best descries the confusion?

A. You are having a communication breakdown with him

B. You have a really big schedule on the project

C. He lacks project management training

D. He is incorrectly calling a schedule a project management plan

D

In this question, could the request also refer to the "Project Charter?

admin's picture

No. D is correct answer