Time Mgmt question
Submitted by cplusplus on Tue, 04/27/2010 - 10:43
In Estimate Activity Durations process, which of the following is not an assumption?
Choice 1 Existing conditions
Choice 2 Availability of information
Choice 3 Length of the reporting periods
Choice 4 Project scope
Please also briefly explain.
Thank you all.
Forums:


ChandraR
Tue, 04/27/2010 - 11:18
Permalink
Answer Choice 4
'Project Scope' is not an assumption. Scope is defined and WBS is already developed b4 Time Management activities get started.
Chandra
swamy_akella
Tue, 04/27/2010 - 11:19
Permalink
I believe the correct answer
I believe the correct answer to be 4. There can be assumptions in project scope, but project scope can't entirely be an assumption. Also, Define Scope process should have been completed before Estimate Activity Durations.
ambahnaresh
Tue, 04/27/2010 - 14:04
Permalink
Whole Project Scop can not be
Whole Project Scop can not be assumptions.