Question - Wording EAC
Submitted by philzs on Mon, 03/16/2015 - 13:10
121. Budget at completion (BAC) is no longer viale. You need to develop a new EAC forcast assuming current variances would continue in the future. Which Formula is good ?
A ) EAC = AC + ETC
B ) EAC = EAC + (BAC -EV)
C) EAC = EV/PV
D ) EAC = BAC / CPI
What do you think and why
Forums:


akbar.azwir
Mon, 03/16/2015 - 15:34
Permalink
The keyword is the
The keyword is the explanation that the current variations will continue during the project, so the answer is D, EAC=BAC/CPI
Checkout the EVM Calculator in magnaqm.com to play around with different EAC formulas and observe the difference.
Good luck
philzs
Mon, 03/16/2015 - 23:56
Permalink
thanks,
thanks,