Question related to EAC
Submitted by hemald on Wed, 08/19/2015 - 12:17
Hello
Please help me by explaining why Ans 4 is correct.
As a project manager you realize that the initial budget cost, Budget at Completion (BAC) for your project is no longer viable. You need to develop a new Estimate At Completion (EAC) forecast assuming current variances would continue in the future. Which of the following formula should you use for calculating EAC? Here AC is the Actual Cost , EV is the Earned Value, PV is the Planned Value .
- 1) EAC = AC + ETC
- 2) EAC= AC+ (BAC - EV)
- 3) EAC = EV/PV
- 4) EAC = BAC/ cumulative CPI
Ans: 4
Forums:
gomsy
Thu, 08/20/2015 - 18:38
Permalink
The answer is correct as there are no variances
The answer is correct as there are no variances. Hence, EAC = BAC/ cumulative CPI
afaqazi
Fri, 08/21/2015 - 09:52
Permalink
In examination there many be
In examination there many be many relevant and irrelevant knowledge that can confuse you. But you must pick up the most revelent point from the question. Here in the question, it clearly emphasis on the "assuming current variances would continue in the future". Which means, you must continue with the same variance and find out what is your EAC. Hence answer is option#4
hemald
Sun, 08/23/2015 - 04:21
Permalink
Thanks all for clarifying this.
Thanks all for clarifying this.
NISHA
Fri, 08/28/2015 - 05:10
Permalink
EAC
There will be three situations to calculate EAC
EAC=AC+(BAC-EV)(Atypical-When the varience was only once due to some reason and now you are going to move forward as planned)
EAC=AC+ETC(Manual)(When you knkw that whatever you have planned is flawed and you need to estimate now..so it will be Actual cost + Bottom up estimating)
EAC=BAC/CPI(Typical-When you know that whatever is the rate of moving forward the same will move forward for the rest of the project)
Check below link for more information.
https://www.youtube.com/watch?v=tSH77PGFR2I
Thanks and regards
Nisha Rai,PMP