question on probability
Submitted by vijayavadrevu on Wed, 04/24/2013 - 18:02
Regression testing has optimistic estimate of 6days, pessimistic estimate of 36 days, and most likely of 21 days. Calculate probability that regression testing to be completed in 2 - 3 weeks
A)0.526
B)0.998
c)0.682
D)0.956
Answer is given as C
Can some one explain?
Forums:


crushPMP
Wed, 04/24/2013 - 18:37
Permalink
PERT = (6+36+21*4)/6 = 21 =
PERT = (6+36+21*4)/6 = 21 = 3 weeks
2 weeks is 1 standard deviation away = 1 - (3-2)/3 = 66.666%
Ans C is the closest
sspawar
Thu, 04/25/2013 - 05:03
Permalink
This question can be solved
This question can be solved like this:
O = 6
P = 36
M = 21
Expexted(Mean ) = 21 (by pert formula (6+4*24+36)/6)
SD = (P - O)/ 6 = [(36 - 6) /6] =5 DAYS
3 WEEKS = 21 DAYS = MEAN ----- PROBABILITY of completing job in 3 weeks will be at Mean , = 50%
2 WEEKS = 14 DAYS ~ - 1SD (21-14 ~ 5) from mean ----- PROBABILITY of completing in 2 weeks will be =[50 -( 68.26/2)]%
= 50 -34.13 = 15.87%
because +/- 1SD = 68.26%
hence PROBABILITY OF COMPLETING JOB IN 2-3 WEEKS will be = 50 -15.87 = 34.13 % or 0.3413
Hence no one option is correct here.
it is half of the 0.6826
-------------------------------------------------
exact of 21-14 = 7 days will be (7/5)SD = - 1.4SD, EQUIVALENT PROBABILITY OF -1.4SD WILL BE (from standard probabity chart = 0.4192 (Refer blog post dated 30th May at er-sspawar.blogspot.in
hence exact probability of 2-3 weeks will be = 0.5-.4192 = 0.0808
bkthakkar
Thu, 04/25/2013 - 06:00
Permalink
Agree, Completely with
Agree, Completely with you
Explanation was truly amazing
sspawar
Thu, 04/25/2013 - 06:32
Permalink
SD = 5
50 % PROBA
6
M =21
36
1SD = 5
41.92% PROB
MEAN
6
14
21
30
.-3SD
.-1.4SD
.+3SD
SD = 5
8.08
%
41.92% PROB
6
14
M =21
36
.-1.4SD
2week
3week
san
Thu, 04/25/2013 - 07:38
Permalink
Thank you for the detailed
Thank you for the detailed explanation. I understood the second part but the chart will not be available in the exam.
So, I am trying to understand first solution.
I am cleared till PROBABILITY of completing job in 3 weeks
I am not understanding as how you arrived PROBABILITY of completing job in 2 weeks
It is mentioned that 1SD (21-14 ~ 5) from mean
that means 50- 7/5(34.13)
But 7/5 value is ignored here.
Please clarify on this point
falcios
Thu, 08/08/2013 - 11:51
Permalink
Is 41.92% the correct answer
Great charts!
Is 41.92% right because that's what I got. It's not one of the answers listed.
The answer is calculating -/+ 1 sd 68%
sspawar
Thu, 04/25/2013 - 09:03
Permalink
I am sure in exam , such
I am sure in exam , such question which requires any references or itself are lengthy, could not be asked.
it is just for understanding the concepts.
I am also sure that this question is not correct.
hence an approximation upto the known values is taken by me.
--------------------------
your doubt
it is corresponding value
for
1sd = area any side of mean = 34.13%
in figure you can imagine 14 days (2 weeks) is 7 days behind of 21 days (mean)
where 5 days = 1sd
it is by approximation considered that 7 ~5 = 1sd (because generally we know = 1sd = 34.13% and we dont know what is corresponding area of 7 (1.4sd) exactly .
and hence by chart in second case, it is shown.
san
Thu, 04/25/2013 - 11:54
Permalink
Thank you for the
Thank you for the explanation..