Question on contract
Submitted by philzs on Mon, 03/02/2015 - 13:29
Guys what do you think of this one
182 Which of the following is NOT an input of the Contract Administration process?
a) Work Performance Information
b) Procurement Management Plan
c) Contract Management Plan
d ) Selected Sellers
Forums:


coolpmp69
Mon, 03/02/2015 - 15:43
Permalink
I think the correct answer is
I think the correct answer is option C - contract management plan.
Also note that this question is referring to PMBOK4 based on the terminologies
philzs
Mon, 03/02/2015 - 21:06
Permalink
Answer is B:
Answer is B:
I don't like that question,
the answer is :
Contract administration process = monitor and control procurement, its when you run a change that has to be made to a specific contract
Contract management plan deal with one contract where procurement mgmt plan deal with many
PMBOK 5 doesnt talk about contract management plan, pretty weird
coolpmp69
Mon, 03/02/2015 - 21:42
Permalink
As I mentioned earlier it is
As I mentioned earlier it is referrign to PMBOK4. So read only PMBOK for exam and solve questions related to pmbok5 not 4 :)