Question#
Submitted by patel07 on Mon, 08/17/2015 - 19:50
pm requires two resources for the project. There are 5 resources in his organization working for another project. PM is lookig for same skills. The project is on schedule and on budget. What tools pm will use to seek the resouces?
1. Pre-Assignment
2. Negotiation
3. Virtual team
4. Acquisition
Forums:
vishwanathkanchipmp
Thu, 08/20/2015 - 06:05
Permalink
2. Negotiation
2. Negotiation
Mogyalas
Thu, 08/20/2015 - 11:10
Permalink
2. Negotiation
2. Negotiation
Meiyazhagan
Fri, 08/21/2015 - 09:06
Permalink
Answer 4
bcoz, all the 5 resources are already engaged in anoother project. so PM has to acquire from outside