Is there any specific cause we do not use Bottom-up Estimating while doing “Estimate Activity Duration” ?
admin
Tue, 02/23/2016 - 08:39
Permalink
You can break down the activity and sum of all tasks would be the estimate of activity duration. In that case it would be called as work break down and not bottom-up estimation.