PMP Question - Which one is correct?
Submitted by Thinhphung on Mon, 06/09/2014 - 05:29
A Project with a total funding of $100,000 finished with a BAC value of $95,000. What term can BEST describe the difference of $5,000?
A. Cost Variance
B. Management Overhead
C. Management Contingency Reserve
D. Schedule Variance
Source: http://www.quizlib.net/PlayingPublicTest.aspx?quizid=47
Forums:


Meiyazhagan
Mon, 06/09/2014 - 07:33
Permalink
Answer C
Management contingency reserve - Because Management reserve equals to project budget - Budget at completion
sunku65
Mon, 06/09/2014 - 08:48
Permalink
Management reserves almost
Management reserves almost equal to 5% of BAC that not included in the BAC.
Answer is C