pleaes help me understand the answer
Submitted by pmp_want2b on Tue, 03/15/2011 - 07:55
Hello,
this is the questioin from the Headfirst. I answered B since stake holder analysis is done while develping the project charter but the correct answer is A. Anyone agrees on the Headforst answer?
Question number: 174 (ref: q0007)
When do you perform stakeholder analysis?
A :When defining the project scope
B :When developing the project charter
C : When creating the project management plan
D : When putting changes through change control
Stakeholder Analysis is one of the tools and techniques of the Scope Definition process. And that shouldn't really be a surprise. After all, the goal of stakeholder analysis is to write down the needs of your stakeholders. And when is it most important to figure out what your stakeholders need? When you're defining the scope of the project work!
Forums:


Awtas
Tue, 03/15/2011 - 22:59
Permalink
A :When defining the project