PERT
Submitted by ppalkonda1975 on Thu, 07/18/2013 - 01:34
Together with your team, you applied three-point estimation on a critical path which consists of two activities. The following duration uncertainties are all calculated assuming a ±3sigma confidence interval. The duration uncertainty—defined as pessimistic minus optimistic estimate—of the first activity is 18 days; the second estimate has an uncertainty of 24 days. Applying the PERT formula for paths, what is the duration uncertainty of the entire path? 94
o 21 days
o 30 days
o 42 days
o No statement is possible from the information given.
whats the answer and explaination please
Forums:


ppalkonda1975
Thu, 07/18/2013 - 14:48
Permalink
anyone can help me with this
anyone can help me with this one?
vikula01
Thu, 07/18/2013 - 17:56
Permalink
duration uncertainty
The duration uncertainty—defined as pessimistic minus optimistic estimate - that can clear confusion which is in the question
cnppmp1
Thu, 07/18/2013 - 14:58
Permalink
42
The information provided on PERT and uncertainty I think should be ignored and just look at the activity duration for the two activities mentioend and addup, 24+18=42
Regards
CN Patil
pmpnewster
Thu, 07/18/2013 - 15:18
Permalink
Formula: Std Devn = Duration
Formula: Std Devn = Duration Uncertainty / 6
For 1st activity, StdDev1 = 18/6 = 3 ==> Variance1 = 3^2 = 9
For 2nd activity, StdDev2 = 24/6 = 4 ==> Variance2 = 4^2 = 16
Variance of critical path = Var1 + Var2 = 9 + 16 = 25
Std Dev of critical path = sqrt(25) = 5
==> Duration Uncertainty of critical path = 6*StdDev = 6*5 = 30 days
Choice 2: 30 days
ppalkonda1975
Thu, 07/18/2013 - 15:49
Permalink
choice 2 is correct
choice 2 is correct answer
but how do we know we need to calculate std dev - duration uncertainty/6? I thought this calcuation was already done i.e. deviation = p-o/6 and then we have the values listed in the question....
where can i read more on these types of topics?
ppalkonda1975
Thu, 07/18/2013 - 15:53
Permalink
As i read more into your
As i read more into your answer i udnerstand better
first we need to get
1. the std deviation
2. then variance and add variance (addition of variance cannot be the answer, you need to calculate back again the std deviation
3. calculate std deviation...
only the last part i need clarification for where you said Duration "Uncertainty of critical path = 6*StdDev = 6*5 = 30 days". ??
pmpnewster
Thu, 07/18/2013 - 16:26
Permalink
I have used the formula:
I have used the same formula as in my earlier post: Std Devn = Duration Uncertainty / 6
==> Duration Uncertainty = 6*Std Devn
Does that answer your question?
Regards.
ppalkonda1975
Thu, 07/18/2013 - 16:35
Permalink
yup it does..straight
yup it does..straight forward...but too much thinking can screw up ....thanks!!