Can you help me answer this questions?
You are running a project for a customer based on a cost-reimbursable contract with the following terms:
Target costs: | $ | 1,000,000 | ||
Fixed fee: | $ | 100,000 | ||
Benefit/cost sharing: | 80% / 20% | |||
Price ceiling: | $ | 1,200,000 |
Which is the PTA (= point of total assumption, break point) of the project?
|
||
$1,300,000 | ||
$1,500,000 | ||
$80,000 | ||
$1,125,000 |
Forums:
admin
Tue, 03/01/2016 - 11:06
Permalink
Check this link http:/
Check this link http://pmzilla.com/pta-point-total-confussion-please-help
NSB
Tue, 03/01/2016 - 14:06
Permalink
Thank you