oliver lehmann questions from 75 question pool PTA related. - plse help

Can you help me answer this questions?

 

You are running a project for a customer based on a cost-reimbursable contract with the following terms:
 

Target costs:     $ 1,000,000
Fixed fee: $ 100,000
Benefit/cost sharing: 80% / 20%
Price ceiling: $ 1,200,000

Which is the PTA (= point of total assumption, break point) of the project?

 

  $1,300,000
  $1,500,000
  $80,000
  $1,125,000

 

admin's picture

Thank you