When to use the right Estimate ?
Submitted by philzs on Fri, 03/20/2015 - 12:07
q171 Between ROM, Budgetary and Definitive, when to use them ?
Let's say the question have no context just that, We are in planning, what estimate would you take
I toght that.....
Initiating or before = ROM
Planning = Budgetary
Executing ( close to the end ) = Budgetary
Forums:


akbar.azwir
Fri, 03/20/2015 - 17:19
Permalink
ROM, a ballpark estimation of
ROM, a ballpark estimation of how much is the cost to complete the project. The level of detail is small. The variance is really high, can be up to 100% variance.
Budgetary, a more detailed estimation. Using a top down approach, usually using an analogous or parametric estimating. The variance is way less than ROM.
Definitive, a more detailed estimation that uses a bottom up approach. This is something that you can achieve after you have your WBS. The variance is less than Budgetary.
ROM -> Initiating
Budgetary -> Planning (early stage)
Definitive -> Planning (progressive elaboration)