EAC value ??
Submitted by anmol2701 on Fri, 02/20/2015 - 11:08
You are a project manager for creating an online mega store. Customers can log in to the online store and order any item ranging from household to luxury items. The project is underway. You accept project costs to date and assume future work (ETC) will be performed at the budgeted rate. If BAC = 700, ETC = 175, PV = 200, AC = 100, EV = 150, and cumulative CPI = 1.5, what is the EAC?
Options are 1) 540 2) 650 3) 500 4) 450
Forums:


coolpmp69
Fri, 02/20/2015 - 14:00
Permalink
EAC forecast
EAC =AC+(BAC-EV)
= 100 +(700-150)
= 650
correct answer is option 2 )650
anmol2701
Sat, 02/21/2015 - 11:39
Permalink
Correct option.
Yes sir. I too solved it by referring PMBOK page 224.