Question duration estimate

"which of the following statements about the creation of duration estimates is incorrect?"
1 MAathemmatical analysis like CPM, gERT, PERT indicate the dates on which the activity can be scheduled given resource limits and other contraints
2 Suration compression techniques, including fast tracking and crashing can help in decreasing the project Schedule
3 WBS classification alllows for useful activity ordering and sorting
4 the duration of the project is the sum of the duration of all the tasks in the project

What do you think of the option 1 ?

what is the source of the is question?

Looks like 1. Not all consider resource constraints.

admin's picture

Even 4 is not correct, Sum of duration of all tasks is not the project duration. Sum of duration of tasks on critical path is the duration of project.

pmstudy

question itself is wrong :-).... it has many incorrect options, not just 1.