Question duration estimate
Submitted by philzs on Thu, 02/12/2015 - 13:24
"which of the following statements about the creation of duration estimates is incorrect?"
1 MAathemmatical analysis like CPM, gERT, PERT indicate the dates on which the activity can be scheduled given resource limits and other contraints
2 Suration compression techniques, including fast tracking and crashing can help in decreasing the project Schedule
3 WBS classification alllows for useful activity ordering and sorting
4 the duration of the project is the sum of the duration of all the tasks in the project
What do you think of the option 1 ?
Forums:


coolpmp69
Thu, 02/12/2015 - 14:26
Permalink
what is the source of the is
what is the source of the is question?
YogSam
Thu, 02/12/2015 - 18:27
Permalink
Looks like 1. Not all
Looks like 1. Not all consider resource constraints.
admin
Fri, 02/13/2015 - 05:13
Permalink
Even 4 is not correct, Sum of
Even 4 is not correct, Sum of duration of all tasks is not the project duration. Sum of duration of tasks on critical path is the duration of project.
philzs
Wed, 02/18/2015 - 01:15
Permalink
pmstudy
pmstudy
YogSam
Thu, 02/19/2015 - 13:35
Permalink
question itself is wrong :-).
question itself is wrong :-).... it has many incorrect options, not just 1.