Linkage of Create WBS and validate Scope
Submitted by Anirban Chatterjee on Sun, 02/08/2015 - 08:14
The process create WBS gives output to Scope Baseline which goes to validate scope as per PMBOK figure5-10 page 126. But the input to validate scope as per PMBOK figure5-15 page 133 does not show scope baseline as input. Can somebody explain why there is no linkage?
Forums:


coolpmp69
Sun, 02/08/2015 - 20:24
Permalink
Good question!!
Good question!!
In validate scope, project management plan is one of the inputs which in turn contains scope baseline as described below.
Project management plan (PMP) - describes how the scope will be defined, managed, valdiated and controlled.
PMP contains - scope management and scope baseline.
Scope management plan - how the scope will be verified and accepted
scope baseline - approved version of project scope statement, WBS and WBS dictionary
Hope this helps...let me know if you have any follow-up question.