The stakeholder wants to know the status of the project. The sponsor wants to know the timeline of the project. The project manager creates the document to know how to monitor and control project work. Which project document will you create?
A. Performance Reports
B.Project Management Plan
C.Stakeholder Register
D.Work Performance Document
Forums:


kevinkkyip
Sat, 03/08/2014 - 01:22
Permalink
Performance Reports, which is
Performance Reports, which is an output of the 'Monitor & Control Project Work' process