MOST appropriate thing to do
Submitted by Jp2786 on Tue, 05/27/2014 - 02:27
Which of the following would be the MOST appropriate thing to do during the
executing process group?
a) Forecast when the next milestone will be completed
b) Recommend updates to the Project Management Plan
c) Recalculate how long the project will take
d) Determine if project controls needs to be updates
Pls let us know the rational behind selecting an answer.
Forums:


admin
Tue, 05/27/2014 - 03:54
Permalink
b and d are very generic.
b and d are very generic. Your next milestone should be your first priority. So I would pick a
Sundara.damaraj...
Tue, 05/27/2014 - 05:01
Permalink
Most appropriate thing to do is "D"
A,B and C are M&C processes.
"D" is part of "Perform quality Assurance" which is done in Executing.
kumarks984
Tue, 05/27/2014 - 05:23
Permalink
According to my understanding
According to my understanding, answer should be B since most of the execution processes have a common output of "Project Management Updates"
since Forecasting is done in M&C
Option C is "Control Schedule" - M&C
Option D is "Control Processes" which are part of M&C
sunku65
Tue, 05/27/2014 - 15:00
Permalink
@kumarks984 correct
@kumarks984 correct
Jp2786
Tue, 05/27/2014 - 18:00
Permalink
correct
yes @kumarks984 is correct