MOST appropriate thing to do

Which of the following would be the MOST appropriate thing to do during the
executing process group?
a) Forecast when the next milestone will be completed
b) Recommend updates to the Project Management Plan
c) Recalculate how long the project will take
d) Determine if project controls needs to be updates
 
Pls let us know the rational behind selecting an answer.
admin's picture

b and d are very generic. Your next milestone should be your first priority. So I would pick a

A,B and C are M&C processes.
"D" is part of "Perform quality Assurance" which is done in Executing.

According to my understanding, answer should be B since most of the execution processes have a common output of "Project Management Updates"

since Forecasting is done in M&C

Option C is "Control Schedule" - M&C

Option D is "Control Processes" which are part of M&C

@kumarks984 correct

yes @kumarks984 is correct