If project time and cost are
Submitted by Jp2786 on Tue, 05/27/2014 - 00:12
If project time and cost are not as important as the no. of resources used each
month, which of the following is the BEST thing to do?
a) Perform a Monte Carlo analysis
b) Fast track the project
c) Perform resource leveling
d) Analyze the life cycle costs
Views pls
Forums:
Sundara.damaraj...
Tue, 05/27/2014 - 00:51
Permalink
If Project time and Cost are
A
Jp2786
Tue, 05/27/2014 - 02:24
Permalink
Why?
Why A?
BTW A is not the answer!
admin
Tue, 05/27/2014 - 03:45
Permalink
Since Resources are more
Since Resources are more important than time and cost you should ensure they are adequately loaded through resource levelling. Resource levelling sometimes may increase the schedule or cost , but since they are not as important as number of resources you should not worry about other parameters.
For eg: you have only 4 Earth moving machines available every month. You must ensure that these resources are adequately used and do not have any free time.