Free PMP Exam Sample Question
All,
The following PMP® exam sample question is taken from http://www.free-pm-exam-questions.com - The answer is at the very bottom:
----------------------------
PMBOK Section: Sequence Activities
Process Group: Planning Process Group
Question Type: Calculation
Knowledge Area: Time Management
Difficulty Level: Moderate
Question: "Activity / Duration / Predecessor
A / 2 / Start
B / 4 / A,E
C / 6 / A
D / 3 / B,C
E / 7 / Start
F / 2 / E
What is the critical path?"
A. Start-A-B-D-End
B. Start-E-F-End
C. Start-A-C-D-End
D. Start-E-B-D-End
Hint : Use PDM to calculate.
Reference: PMBOK4 - pg:138
----------------------------
All our free questions are updated to the latest PMBOK® Guide standard. Sign up here to receive the questions via email. We are a PMI Registered Education Provider.
Until next time,
Cornelius Fichtner, PMP
The correct answer is D.
Explanation: The critical path of the data given is Start-E-B-D-End. Hence choice D is correct, while rest of the choices is incorrect.