Free PMP Exam Sample Question

The following PMP® exam sample question is taken from the Free PMP Exam Simulator:

------------------------------

You are managing a nationwide telecom network deployment project. You learned that you are unable to start any civil works before obtaining a government agency's permit, which could take months. The project deadlines are aggressive and you might face penalties if you don't meet them. Obtaining the government agency's permit prior to civil works on any site is an example of which of the following?

A.) Mandatory Dependency
B.) External Dependency
C.) Project Constraint
D.) Project Requirement

------------------------------
Hint: All of the choices are correct in a way but considering the relationship of the permit to the civil work will yield only one correct choice.
------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Please click here for the correct answer and explanation.

Until next time,
Cornelius Fichtner, PMP
President, OSP International LLC - http://www.project-management-prepcast.com