The total authorized budget for your IT project is $160,000 and Management Reserves are $20,000. You want to measure cost performance to see how the project is doing. In this context, the cost performance is against measured which of the following budget amounts?

A.) $180,000
B.) $160,000
C.) $20,000
D.) $140,000

------------------------------

Hint: The Cost Baseline includes all authorized budgets. The Cost Baseline is used to measure the Cost Performance of the project.

------------------------------