What does cost a performance index (CPI) of less than 1.0 indicate?
A) Cost overrun of the estimates
B) Cost underrun of the estimates
C) Cost according to the estimates
D) Early progress
------------------------------
All our free questions are updated to the latest PMBOK® Guide standard. Stop by at http://www.free-pm-exam-questions.com to receive the questions via email. We are a PMI Registered Education Provider.
Until next time,
Cornelius Fichtner, PMP
The Project Management PrepCast™ - http://www.project-management-prepcast.com
The Project Management Podcast™ - http://www.project-management-podcast.com
The Answer is A.