Difference between Project float, free float and float
Submitted by cplusplus on Mon, 05/17/2010 - 00:34
What is the difference between Project float, free float and float, lot of times i see the questions are tweaked to confuse, using all the above 3 terms.
Just want to get a clear understanding.
Thank you all for the helpful information.
Forums:


ChandraR
Mon, 05/17/2010 - 02:22
Permalink
Float explanation
Project Float: the cushion you provide yourself b4 committing a date to customer. Suppose your planned schedule completion is: 15 June and you promise the customer 15 July for completion of deliverables, you are giving yourself a month more time
Free Float: This is the amount an activity can be delayed without delaying the Early Start of subsequent activities. This is the cushion within the activity It is calculated as LS-ES or LF-EF for any activity. Suppose your LS=10; ES=2. You have 8 days of tolerance/slack w/o adversely affecting the project's subsequent activities early start time
Free Float & Float are some times interchangeable. Float is the critical path duration & Non critical path duration difference. If there are several branches in the network diagram, each branch has its float calculated as its critical path duration - branch duration.
e.g. Critical path A-E-F-H : 40 days
Branch A-B-D-H: 36 days, then Float for each of the activities A, B, D, H is 40-36 = 4 days i. e. you can use this 4 days spare time and put up that much delay on any one of the A/B/D/H or any combination of activities - not to exceed 4 days otherwise you will be slipping from the schedule completion
Chandra
ChandraR
Mon, 05/17/2010 - 03:48
Permalink
Here is abetter explanation for Float etc
Pl. read this good article for a better explanation than I provided for Float, Free Float etc
http://www.deepfriedbrainpmp.com/2009/08/total-free-float-cpm-network-di...
Chandra
biswasrahul
Mon, 05/17/2010 - 06:16
Permalink
I choose to differ in the
I choose to differ in the folloing example:
Given that A &H fall on the critical path , do you mean to say you can delay the start time of either A or H w/o affecting the project completion date ?? You prob might not have meant to say so, but the below extract certainly portrays it in that fashion...
"e.g. Critical path A-E-F-H : 40 days
Branch A-B-D-H: 36 days, then Float for each of the activities A, B, D, H is 40-36 = 4 days i. e. you can use this 4 days spare time and put up that much delay on any one of the A/B/D/H or any combination of activities - not to exceed 4 days otherwise you will be slipping from the schedule completion"
ChandraR
Mon, 05/17/2010 - 12:22
Permalink
Biswas rahul: Good point and
Biswas rahul:
Good point and great attention to details! I just illustrated quickly a critical path and a near critical path to bring out the float concept in quantitatively so people can understand. Sure there is no slack on activities common to critical path & non-critical path.
Chandra