CPI when current variances are atypical
Submitted by vijayavadrevu on Sun, 05/26/2013 - 17:39
Please refer to the following diagram:
You know that current variances are atypical, i.e., similar variances will not occur in future. What is the cost performance index (CPI) for the project?
- 0.96
- 1.04
- 1.00
- 1.20
Should we consider the formula, CPI = BAC / EAC or CPI = EV / AC? I have used the first formula (as the variances are atypical) and got CPI as 0.976
Please clarify
Forums:
y0zh
Sun, 05/26/2013 - 18:24
Permalink
Ev/ac, since there wont be
Ev/ac, since there wont be variances in the future
vijayavadrevu
Sun, 05/26/2013 - 18:39
Permalink
http://pmi.books24x7.com/asse
http://pmi.books24x7.com/assetviewer.aspx?bookid=45514&chunkid=397723927
As per this link,
EAC = BAC / CPI Use formula if current variances are thought to be typical in the future.
EAC = AC + BAC - EV Use formula if current variances are thought to be atypical in the future
hence confused and posted the question. can you / someone give clarification as to which formula is to be used?
y0zh
Sun, 05/26/2013 - 21:00
Permalink
Why are you looking for
Why are you looking for forecasting? The question is to give the actual CPI
vijayavadrevu
Mon, 05/27/2013 - 02:31
Permalink
"You know that current
"You know that current variances are atypical, i.e., similar variances will not occur in future."
I am getting confused looking at sentences like this
Thank You
sanskrit
Mon, 05/27/2013 - 17:32
Permalink
Take it easy.
Lets take simple example,
So based on Three informations above, You have
No Take Two scenerios
Scenerio 1
What it means is your EAC has to be calculated assuming CPI will remain same i,e 0.8 for the rest of the project,
Scenerio 2
What it means is your EAC has to be calculated assuming CPI will be 1 for the remaining period of project
So using same logic as scenerio 1
Estimate at completeion will be = Actual Cost + Project Cost to finish rest of the Work which is AC + (BAC- EV )/CPI
i.e EAC = AC + (BAC-EV)/CPI Here as similar variances will not occur in future So CPI is 1
i.e EAC = AC + (BAC-EV)/1 = AC + BAC -EV
:)
vijayavadrevu
Mon, 05/27/2013 - 18:13
Permalink
Thank You so much @sanskrit
Thank You so much @sanskrit
sanskrit
Mon, 05/27/2013 - 22:40
Permalink
You are always welcome
Anytime.