controlling the key stakeholder engagement

Mary is currently focusing on controlling the key stakeholder engagement on her project. The project management plan is an essential input to this process. Which of the following components of the project management plan is least likely to be utilized during this process?

1. Stakeholder communication needs and expectations
2. Project management processes selected for the project
3. Change management process
4. Human resource requirements

....Your views pls.