Submitted by sachinagg77 on Thu, 11/25/2010 - 07:59
What do you think the correct answer is? Kindly share the reasoning behind your answer.
The source I got this question from indicates (d) as answer. I feel (b) should be the correct answer as making no payments to the contractor would certainly halt (or delay) the project.
Forums:


raj9
Mon, 12/06/2010 - 15:47
Permalink
Answer d
Contract term is single,lumpsum payment at the end of satisfactory completion of the work. But contractor;s request is different than agreed contract.
Hence d is the answer.
thanks,
Raj
peterpan28@gmail.com (not verified)
Wed, 03/30/2011 - 00:30
Permalink
Answer is B.Refer our web
Answer is B.
Refer our web site www.mypmpexamprep.com