The scope of your project is very well defined and you have completed all the work described in the contract to your satisfaction, but you think your buyer is not happy with the work. What should you do? 
 
 
  Choice 1 Go through arbitration proceedings to ensure that disputes are resolved
 
  Choice 2 Talk with senior management about changing the scope of the project to accommodate requirements that would satisfy the customer
 
  Choice 3 Ask customer for inputs and get her advice on changes that need to be made
 
  Choice 4 Move to contract close-out
jvleminc's picture

 Scope is well-defined and all work is done as per contract -> close the project. 

 I thought initially option 4 as answer but then i look at the word "think" and then changed my answer....

think something overthinking is not good as well i guess

 

Choice 3

Note that getting the customer's input and suggestions does not necessarily mean agreeing to her requested changes.

 

What's the official answer?

 

Regards.

 

 option 4 is the answer....i also chose option 3