Confirmation on answer needed

Hey,


I need some confirmation that my answer is correct, below I had this question in a prep-exam. The explanation sentence is correct regarding releasing the team is correct, but close procurement is not the final step.I could have 10 close procuremetn process until aI finally reach the project closure.


Thanks for your help in advance


Which of the following is the last activity performed while closing a project?


A. Creating leasons learned
B. Releasing resource assigned to the project
C. Verify Scope
D. Close Procurements


My answer is B,
according to the prep-exam it would be D


Explanation: Close procurement is the final step in closing a project. You should not release the team until after you document leasons learned.


 

admin's picture

Absolutely wrong in my opinion. There can be many vendors on a project and you can close the procurements at any stage of the project.


Once resources are released no further work can be done. Hence it would be last activity in this case. Remember the answer always has to be evalated , we cannot generalize that releasing resources would always be last activity.

Hello:

I agree with admin. Releasing the resources is the last step in project closure. Its not procurement closure.

Kindly check the verifiability of the site that you are doing the answers from. Its v v important.

Thanks,
KK!