Closing related query

I am confused regarding the order in which these two processes occur...


Is it Close project followed by close Procurements or


Close Procurements followed by close project?

Its pretty simple and nothing 2 be confused


ask these questions to ur self and uill get an answer, its logical...


When do u plan/conduct procurment is it after the project initiates or before ??


its like a nested IF loop in a coding (if you know coding) or more logical is that, before you lock e the main door of ur house, u lock all the other doors that are inside ur house...


u procuer some thing only to help u support the project, not to support outside of ur process,


If you still ve doubts refer to Rita's process chart....