Calculate Estimated cost while SV and CV are given
Submitted by samy001us on Wed, 05/19/2010 - 04:03
The schedule variance for a project is 20%.The Budget for the project is $480,000. What is the estimated cost on project completion if the EV and AC of the project currently is $48,000 and $60,000 respectively and if the current cost variance and schedule variance is expected to continue in future?
Kindly help
Forums:


chowdary2104
Wed, 05/19/2010 - 04:41
Permalink
Answer is B
Key Point: Current Vairance is expected to continue in future. Then here is the formula for EAC:
EAC = BAC/CPI
First Calculate CPI = 48,000/60,000 = 0.8
You know the BAC = 480,000
Then apply the formula: EAC = 480,000/0.8 = 600,000.
So answer is 'B'
Regards,
Lakshmi VR Chowdary A