You are the project manager in an aircraft manufacturing company developing a new range of supersonic fighter planes. Since government approval and involvement are essential, you hire a lobbying firm to get government support to prevent unnecessary changes in your project. Which process is this an example of? 
 
 
  Choice 1 Perform Integrated Change Control
 
  Choice 2 Risk Management
 
  Choice 3 Cost Management Plan
 
  Choice 4 Develop Project Management Plan

 

 

Choice 2 Risk Management

 

Regards.

 

 Me too selected 2.

 1

The lobbying firm is not the gate keeper of changes - They are hired by us to work with government to prevent the changes ( risk ) - which is a risk management plan .

As per test authors, the right answer is Choice 1

 Hence the answer is  1