Some exam questions

Ok I remember these question from my last exam, I am still confused about it,

 

1. Quality mangement plan is based on Project organization's policy or customer's requirements.

 

2. Risk in project log, appeared in the end of the project, team didn't know about it. What was the cause? Communications Mangement Plan?

 

3. Expert will be available after 2 months - Resource leveling, CPM, CCM?

 

 

Thank you.

1. Quality mangement plan is based on Project organization's policy or customer's requirements :

 
It is definitely based on customer's requirements. The customer usually defines what is acceptable
and what is not.  So based on that we need to what is acceptable quality, 
how will it be measured andthen determine what we will do to meet those requirements.
 
 
2. Risk in project log, appeared in the end of the project, team didn't know about it. What was the cause? Communications Mangement Plan?
 
Could you please elaborate this question?
 
 
3. Expert will be available after 2 months - Resource leveling, CPM, CCM?
 
Resource Levelling - As per Rita, Resource Levelling is a little used tool in PM software, it allows you to level the peaks and valleys of 
resource use from one month to another, resulting in a more stable number of resources used in your project.